Exporting and importing information using Asta Site Progress

You use the Site Progress tab of the Backstage view to export information from your Asta Powerproject project(s) so that it can be updated using Asta Site Progress. Project information - information relating to those tasks that should be in progress or complete during or just after the current working period - is exported to the Cloud, from where it can be updated by each Mobile user.

Once users have updated the project information remotely using Asta Site Progress, you use the Site Progress tab to import the information back into your Asta Powerproject projects.

You should export and import information on a regular basis. For example, it would be good practice to export uncompleted work every Monday afternoon for it to be updated on-site during the following week, then import the updated information every Monday morning.

Note that you must ensure that nobody has the project(s) concerned open in Asta Powerproject while you export and import project information.

You can export and import information in a number of ways, which are described below.

Exporting information to Asta Site Progress

Importing information from Asta Site Progress into your projects

Note that each job that is exported to Asta Site Progress can be exported only once. This means that if a Mobile user has access to more than one mobile device, they can only access their project information each working period on one mobile device: they cannot access the same period's information on more than one device. For this reason, if a user upgrades their mobile device, they must ensure that they have submitted all of their project information on their old device before they discontinue using the old device, as they will not be able to access the same project information on their new device; they will only be able to access project information relating to new periods on their new device.

Restoring jobs that are overwritten accidentally

If a Mobile user submits their changes at the end of a working period and you attempt to export a new job to the user before importing the submitted job, Asta Site Progress warns you that if you continue, you will overwrite the Mobile user's last job which has not yet been imported. If you ignore this warning, the information that the user submitted is lost, as the newly-exported job overwrites the job that was submitted but not imported.

Asta Site Progress backs up each job automatically in the Cloud when it is submitted by a Mobile user, so if this happens, you can restore the overwritten job from the automatic backup.

To do this:

  1. Click the Site Progress tab of the Backstage view.
  2. Click Log in and sign into Asta Site Progress configuration using the window that appears.
  3. On the Site Progress tab of the Backstage view, in the Displaying jobs field, select Exported not in use. The grid displays jobs that have been exported, but that have not yet been updated by a Mobile user.
  4. Right-click the job that you want to restore from the automatic backup and select Restore backup. The exported job is overwritten by the job from the backup. You can now import the job.

If you need to restore an accidentally-overwritten job from the automatic backup, you must do this before exporting any further information to the Mobile user, as carrying out a further export would overwrite the backup.

Related Topics:

Overview of the progress reporting process

Approving or rejecting progress

Viewing Asta Site Progress logs

Configuring Asta Site Progress

Exporting information from copies of projects