Overview of the progress reporting process
The following illustration shows the way in which Asta Siteprogress Mobile is used to update project information with remotely-recorded progress. Steps that are carried out by Administrators are shown in blue; steps carried out by Mobile users are shown in red. More information on each stage of the process is given beneath the illustration:
Export jobs
Asta Siteprogress Mobile Administrators use the Site Progress tab of the Backstage view to export project information from your Asta Powerproject projects. Typically, the export is done once a week, usually at the start of each week - Monday afternoon would be a good time to do this. Project information - information relating to those tasks that should be in progress or complete during or just after the current working period - is exported to the Cloud, from where it can be updated by each Mobile user using a mobile device.
Record progress
When a Mobile user accesses Asta Siteprogress Mobile at the start of a working period - usually a week or fortnight - information relating to the tasks on which they are due to work during the working period are downloaded. Mobile users select the project that they want to update and browse through the project hierarchy to locate the chart or summary group that represents the site that they want to update. They can then use Asta Siteprogress Mobile to update individual tasks and to tick off the build stages that have been completed for each plot. They can also associate photographs and notes with particular tasks or build stages.
Submit
Once a Mobile user has finished recording progress - usually at the end of the week - they submit the information that they have recorded using Asta Siteprogress Mobile.
Import into Asta Powerproject
Once a Mobile user has submitted their progress information, Asta Siteprogress Mobile Administrators use the Site Progress tab of the Backstage view to import the information back into your Asta Powerproject projects. As with the export, the import is typically done once a week. If you export every Monday afternoon, Monday morning would be a good time to carry out the import.
Approve progress (optional)
Approving Asta Siteprogress Mobile progress information is an optional step - approval takes place only if the Imported progress requires approval check box on the Import tab of the Site Progress Settings dialog is selected. If Asta Siteprogress Mobile is configured to require approval, Administrator users accept or reject the progress that has been recorded by Mobile users. Any progress that is rejected is not imported into the appropriate Asta Powerproject project.
Reschedule project
Once updated project information has been imported into the Asta Powerproject projects, the projects can be rescheduled in order to move uncompleted tasks beyond the report date of the last-used progress period. Once the projects have been rescheduled, the process can be started again, beginning with the export.
The following illustration shows the way in which Asta Siteprogress Mobile is used to update project information with remotely-recorded progress when field evidence is collected. Steps that are carried out by Administrators are shown in blue; steps carried out by Mobile users are shown in red. More information on each stage of the process is given beneath the illustration:
Export jobs
Asta Siteprogress Mobile Administrators use the Site Progress tab of the Backstage view to export project information from your Asta Powerproject projects. Typically, the export is done once a week, usually at the start of each week - Monday afternoon would be a good time to do this. Project information - information relating to those tasks that should be in progress or complete during or just after the current working period - is exported to the Cloud, from where it can be updated by each Mobile user using a mobile device.
Information on the tasks for which field evidence must be collected, and on the individual evidence items that must be collected, is exported when you export information from your Asta Powerproject project(s) so that it can be updated using Asta Siteprogress Mobile.
Record progress
When a Mobile user accesses Asta Siteprogress Mobile at the start of a working period - usually a week or fortnight - information relating to the tasks on which they are due to work during the working period are downloaded. Mobile users select the project that they want to update and browse through the project hierarchy to locate the chart or summary group that represents the site that they want to update. They can then use Asta Siteprogress Mobile to update individual tasks and to tick off the build stages that have been completed for each plot. They can also associate photographs and notes with particular tasks or build stages.
Collect field evidence
If the names of any of the tasks that have exported match the names of tasks in your field evidence template, Mobile users can collect field evidence to prove that those tasks have been completed. Collecting field evidence involves taking a photograph for each evidence item that is associated with a task; each task can have more than one field evidence item associated with it. Asta Siteprogress Mobile automatically saves data relating to where and when the photographs were taken, and who they were taken by.
Submit
Once a Mobile user has finished recording progress - usually at the end of the week - they submit the information that they have recorded using Asta Siteprogress Mobile.
If the Mobile user has collected any field evidence, the field evidence is submitted at the same as their progress information. Any field evidence photographs that they have taken are uploaded to the Cloud at this point.
Approve field evidence
Once a Mobile user has submitted one or more field evidence items, Administrator users receive an email to inform them that field evidence has been submitted. They then sign into Asta Siteprogress Mobile to review the field evidence that has been submitted. Administrators can approve or reject each individual item of field evidence. If they reject an item, they must record a reason for the rejection.
Revise rejected field evidence
If any field evidence items are rejected - for example, because a photograph is not sufficiently clear - Mobile users must revise the rejected items, usually by taking another photograph. They can then resubmit the rejected items, which go through the approval process once more.
Import into Asta Powerproject
Once all the field evidence relating to a job has been approved, an Administrator user can use the Site Progress tab of the Backstage view to import progress back into your Asta Powerproject projects. As with the export, the import is typically done once a week. If you export every Monday afternoon, Monday morning would be a good time to carry out the import.
Field evidence is not imported into Asta Powerproject; the field evidence photographs remain in the Cloud.
Approve progress (optional)
Approving Asta Siteprogress Mobile progress information is an optional step - approval takes place only if the Imported progress requires approval check box on the Import tab of the Site Progress Settings dialog is selected. If Asta Siteprogress Mobile is configured to require approval, Administrator users accept or reject the progress that has been recorded by Mobile users. Any progress that is rejected is not imported into the appropriate Asta Powerproject project.
Reschedule project
Once updated project information has been imported into the Asta Powerproject projects, the projects can be rescheduled in order to move uncompleted tasks beyond the report date of the last-used progress period. Once the projects have been rescheduled, the process can be started again, beginning with the export.
Produce field evidence report
Once an Administrator user has approved all of the field evidence that is required for a plot, they can produce a field evidence report on the plot. Field evidence reports can be produced for a plot at any time before all of the plot's field evidence has been collected, but it makes sense to wait until all of the plot's field evidence has been collected before producing a report.
Field evidence reports, which are produced in PDF format, include a front page that displays general information about the project, your organisation and the selected plot, which you specify when you produce the report. This is followed by information about the tasks that have been carried out on the plot, and the individual field evidence items that have been collected and approved for each task. The tasks and field evidence items appear in the report in the order in which they appear in the field evidence template. For each field evidence item, the report displays the following: