Configuring Asta Powerproject Integration with Procore
To configure Asta Powerproject Integration with Procore's settings:
- Launch Asta Powerproject and open a project from which you want to export data to Procore.
- On the Add-Ins tab of the Ribbon, click Upload to Procore.
- If this is the first time you have launched Asta Powerproject Integration with Procore, the Export Settings dialog appears. If the dialog does not appear, click
on the Powerproject Integration with Procore dialog.
- In the Your company's Procore URL field, enter the URL that you use to access your company's Procore server.
- If you use Asta Powerproject Enterprise, or if you work with projects in which expanded or summary tasks are flagged as 'Is a Project', select the Allow subproject export check box if you want the option to export specific parts of a programme, rather than the whole programme. If you do not use Asta Powerproject Enterprise, and you do not flag expanded or summary tasks as 'Is a Project', leave this check box cleared to simplify things.
If you select this check box, a Powerproject Subproject field appears on the Powerproject Integration with Procore dialog. - If you have access to more than one company or division in Procore, select the Show all companies check box. This gives you the option to export data to projects in Procore from more than one company. If you do not have access to more than one company or division in Procore, leave this check box cleared.
- Click Apply.
Introduction to Asta Powerproject Integration with Procore