Constraining tasks to specific dates

A task's start and finish dates are determined by its duration and the way in which tasks are linked together. However, this only simulates the internal constraints within a project. Other events outside your control, such as authorisations, the release of design documents and immovable deadlines, may also affect the dates on which tasks can start or finish. You should include these external constraints in your plans if possible.

In Asta Powerproject you can specify that a task should start or finish on, before or after a specific date. You do this by setting a start or finish flag on the task. These flags override the internal logic of a project and show the effect of outside influences on your plan.

A finish flag is sometimes known as a required date, because it sets the date by when you require a task to be finished.

Back

Forwards

Marking project milestones

Structuring projects

Related Topics:

Using constraints