Lead/lag links between tasks on the same bar

When you draw a link between two tasks on the same bar, the link has lead/lag time ensuring that the second task does not begin until the first task is finished:

A link between two tasks on the same bar

If you set up a lead/lag link which would cause the tasks to overlap, this link is ignored by the reschedule and the tasks are positioned end to end.