Work Pattern Properties dialog - Time Units tab

You use the Time Units tab of the Work Pattern Properties dialog to specify the precise length of each time unit as it is used in this work pattern. The precise length of a time unit in relation to a work pattern is known as an override. For example, a working day may be 7 hours in one work pattern, but 7.5 hours in another. Specifying the precise length of time units for a work pattern enables Asta Powerproject to convert durations between the different working time units with complete accuracy.