Work Pattern Properties dialog - Details tab

You use the Details tab of the Work Pattern Properties dialog to edit the name of the selected work pattern and to align the shifts of the work pattern so that each shift starts on the correct day. For example, if the work pattern consists of seven days (Monday, Tuesday, Wednesday, etc), you could align the Monday shift to a date on which a Monday falls. You only need to align one shift within a work pattern with a date: the other shifts will then fall on the correct day automatically. If you do not align a shift with a date, the shifts may fall on incorrect days.

How do I...

Related Topics:

Working with dialogs

Creating a new work pattern

Assigning a work pattern to a calendar