Properties dialog - Properties tab
You use the Properties tab of the
Properties dialog to view and edit information relating to the current project
Depending on your access rights, you may not be able to edit the date-related fields on this tab.

To access the Properties dialog, click the File tab, click Properties, then click Advanced Properties.

Field | Description |
---|---|
Name | Enter a descriptive name for the project |
Short name | Enter a short name for the project |
Status | Indicates whether the project is a destination project that has been booked out from a master project. |
For | Enter the name of the organisation or individual for whom the project |
By | Enter the name of the person who has planned the project |
Default tab colour |
Select a colour to apply to the tabs that appear at the top of each view by default. Selecting a different colour for each of your projects makes it easier to identify which views belong to which project when you have more than one project open at the same time.
|
Start date | The start date of the first task in the project |
Finish date | The finish date of the last task in the project |
Duration | The period of time taken by the project |
Duration unit | Select the time unit in which you want the duration to be displayed. |
Imposed start |
The date at which the project
Note that if you change the imposed start date to a date that is later than the report date of one or more existing progress periods, a warning appears. If this warning appears, click OK to amend the report dates of your progress periods so that they start on or after the new imposed start date, click Close to set the new imposed start date but leave the report dates of the progress periods unaffected, or click Cancel to abandon your change to the imposed start date. If you click Close, you will need to edit the report dates of the progress periods manually.
|
Imposed finish |
The date at which the project
|
Date zero |
The date at which you want unit numbering in any "elapsed units" or "working units" line that you display in the date zone to begin in the date zone. Setting a "date zero" is useful if, for example, you want to set up a line in the date zone showing elapsed days and have it start numbering from a specific date. If you specify a project-wide "date zero" in this field, it is applied to all new views that you create. However, each view can have its own individual "date zero" - specified in the Date zero field on the Dates/Scales tab of the Date Zone Properties dialog.
If a "date zero" has previously been specified for any individual views and you want them to use the project-wide "date zero", clear the check box in the Date zero field on the Dates/Scales tab of the Date Zone Properties dialog.
If you choose not to specify a "date zero", the start date of the first task in the project - or the imposed project start date, if one has been specified - is used to define the point at which unit numbering in any "elapsed units" or "working units" line should start.
You can configure spreadsheet cells that display "Date/Time"-type fields to display the time period between the "date zero" that you specify and the date or time that the field represents, measured in elapsed days, elapsed weeks or elapsed months.
|
Delivery date |
The date on which a project must be delivered. You can specify a delivery date for the programme of projects, and a delivery date for each chart or summary group that has been identified as being a project. You can use a project's delivery date as a deadline when rescheduling. If you do this, rather than using the finish date of the last task in the project, the project's late and free finish dates are set to the delivery date when rescheduling and float is calculated out to the project's delivery date. A delivery date provides a deadline for all tasks in the project, so any tasks that exceed the delivery date have negative float (ie they become super-critical) following a reschedule.
The delivery date is also used when checking the quality of a schedule to calculate the project's maximum duration, which is the difference between the project's start date and its delivery date.
|
Progress method |
Choose whether progress on
In very large projects, you may find that progress calculations take a long time. You can speed things up by selecting an 'approximate' method; you can speed things up even further by selecting 'None' in this field to disable progress calculations for parent tasks. If you do this, parent tasks do not display progress at all.
|
Progress date | The average date up to which the whole project |
Report date | The report date of the progress period used most recently in the project or group project. |
% complete | The total duration percent complete of the project or group project. |
Use calculated overall % weights |
Select this check box to calculate the overall percentage complete weighting of
Calculating progress on parent tasks according to overall percentage complete |
Effort (demand) | The total amount of scheduled effort in the project |
Work | The total amount of work undertaken by permanent resources in the project |
Cost | The total cost of the project |
Income | The total income to the project |
Ignore satisfied costs in roll-ups | Select this check box to ignore costs of satisfied demand allocations in cost totals on parent tasks, or clear the check box to include them. |
Number of tasks | The number of tasks in the project |
Number of links | The number of links in the project |
Number of logged on users | The number of users currently logged into the project, or into the group project and any of its subprojects (Asta Enterprise only). |
Default view |
Select the view that you want to display initially when the project is opened
|
How do I...

Enter the name of the organisation or individual for whom the project

Enter the name of the person who has planned the project

Select a colour to apply to the tabs that appear at the top of each view by default in the Default tab colour field. Selecting a different colour for each of your projects makes it easier to identify which views belong to which project when you have more than one project open at the same time.

Specify a date in either the Imposed start or Imposed finish field. You cannot impose both a start date and a finish date.

Specify a date in the Date zero field.

Specify a date in the Delivery date field. You can specify a delivery date for the programme of projects, and a delivery date for each chart or summary group that has been identified as being a project. You can use a project's delivery date as a deadline when rescheduling. If you do this, rather than using the finish date of the last task in the project, the project's late and free finish dates are set to the delivery date when rescheduling and float is calculated out to the project's delivery date. A delivery date provides a deadline for all tasks in the project, so any tasks that exceed the delivery date have negative float (ie they become super-critical) following a reschedule.
The delivery date is also used when checking the quality of a schedule to calculate the project's maximum duration, which is the difference between the project's start date and its delivery date.

Choose whether progress on parent tasks is calculated according to the child tasks' cost percent complete, duration percent complete, effort percent complete or overall percent complete in the Progress method field.

Select the Use calculated overall % weights check box to calculate the overall percentage complete weighting of expanded and summary tasks automatically based on the weightings of the tasks they contain, or clear the check box if you want to enter your own weightings for expanded and summary tasks manually.

Select the view that you want to display initially when the project is opened
Editing the properties of projects and charts
Specifying a start or finish date for a project
Specifying a delivery date for a project