Print dialog - Calendar tab
You use the Calendar tab of the Print dialog to specify the way in which calendar views are printed. You can specify the hours of the day for which you want to print calendar information for each date, and the range of dates that you want to print.
This tab appears on the Print dialog only when you are printing a calendar view.

To access the Print dialog, click the File tab, click Print, then click Print Options.

Field | Description |
---|---|
Start (hour) |
Select the hour - using the 24 hour clock - at which to start printing calendar information for each date. This should correspond to the start of working time on the selected dates, and prevents your printout from including information on non-working time, in which tasks and allocations will not be present.
The time you select in this field does not apply when the calendar view you are printing is displayed in 'Month' view. |
End (hour) |
Select the hour - using the 24 hour clock - at which to stop printing calendar information for each date. This should correspond to the end of working time on the selected dates, and prevents your printout from including information on non-working time, in which tasks and allocations will not be present.
The time you select in this field does not apply when the calendar view you are printing is displayed in 'Month' view. |
Current view | Click this radio button to include the entire view in the printout, from the earliest task or allocation in the view to the last. |
Choose dates | Click this radio button to print calendar information between a range of dates, which you specify in the From and To fields. |
From... To |
To print information between a range of dates, enter a range of dates in the From and To fields.
If you leave both fields blank, all information is printed; if you leave the From field blank, information is printed from the project start date to the To date; if you leave the To date blank, information is printed from the From date to the project finish date.
You can specify these dates as variable dates - for example 'Today', 'Month start' and 'Year end' - rather than as specific dates. You might want to do this in order to print information relating to the current week, month or quarter - by specifying 'Week start' and 'Week end', 'Month start' and 'Month end' or 'Quarter start' and 'Quarter end'. |
How do I...

Select the hours - using the 24 hour clock - at which to start and end printing calendar information for each date in the Start (hour) and End (hour) fields. Specifying these times, which should correspond to the start and end of working time on the selected dates, prevents your printout from including information on non-working time, in which tasks and allocations will not be present.

Click the Current view radio button to include the entire view in the printout, from the earliest task or allocation in the view to the last, or click the Choose dates radio button to print calendar information between a range of dates, which you specify in the From and To fields.