Setting a start or finish flag

To set a start or finish flag on a task:

  1. Select the task and position it so that it starts or finishes on the appropriate date.
  2. Do either of the following:
    • With the task selected, on the Home tab, in the Schedule group, click the Constraint Flag dropdown.
    • Right-click the task and select Constraint Flag.
  3. Select the type of start or finish constraint that you want to apply to the task.

A flag is assigned to the start or finish of the task, depending on whether you have selected a start or finish constraint.

You can configure the spreadsheet to highlight start and finish dates that are constrained.