Managing a project's baselines

You use the Manage Baseline Snapshots dialog to view details of the baselines that have been created of a project's pull plans. You can specify whether individual baselines are available to be displayed on the whiteboard, and delete any baselines that you no longer need.

By default, the dialog displays every baseline that has been taken, of all of the project's pull plans. You can filter the baselines that appear in the dialog, to display only those that were taken within a specific date range, and only those that relate to a specific pull plan.

To access the Manage Baseline Snapshots dialog:

  1. Click Projects in the left pane. The Projects page appears.
  2. Click a project in the list. The Project Details page appears.
  3. Click Settings at the top of the page. The Project Settings page appears.
  4. Click Manage Baseline Snapshots.

Related Topics:

Creating baselines and comparing pull plans against them

Configuring project settings

Using a whiteboard to manage pull plans