Creating projects in Asta Connect
You use the New Project page to create a project - a master schedule - from scratch in Asta Connect. You can do this as an alternative to using a master schedule that has been created in another application such as Asta Powerproject into Asta Connect.
To access the New Project page:
- Click Projects in the left pane. The Projects page appears.
- Click New Project.
- Click Create a New Project.
To create a new project from scratch in Asta Connect:
- On the New Project page, enter a descriptive name for the project in the Project Name field. This is the only mandatory field on this page: the other fields are optional.
- If the project relates to a contract, enter the number of the contract in the Contract Number field.
- Enter the project's sector, for example Commercial or Residential, in the Sector field.
- Enter the approximate financial value of the project in the Value field.
- Select the currency in which the value is calculated in the Currency field.
- Enter the dates on which the project will start and finish in the Start Date and Finish Date fields.
- Click the Use Project Start Date for Week Numbering toggle to start whiteboard week numbering on the project start date - as specified on this page - for this project's pull plans, or turn off the toggle to number weeks according to the ISO week date system.
- Enter the physical location at which the project will take place in the Location field. This could be a town, a city, or a full address.
- Enter the region in which the project will take place, for example North West or South East, in the Region field.
- Enter the postcode of the project location in the Postcode field.
- Click Save. The project is created and you are taken to the Projects page, where the new project appears in the project list.
Once you have created a project, you can start creating activities in its master plan.
Importing projects into Asta Connect
Viewing and editing project details