Select Link Ends dialog
You use the Select Link Ends dialog to select the tasks to or from which you want to create links. If you are moving a link from one task to another, you use this dialog to select the single task to which you want to move the link. The dialog displays all tasks that meet the criteria you have specified on the Link From/To dialog.
You can sort the tasks that are displayed in the dialog alphanumerically by any of the columns. For example, to sort the tasks by their task ID (WBN), click the heading of the Task ID (WBN) column; to sort the tasks by name, click the heading of the Name column.

The Select Link Ends dialog appears when you click the Link button on the Link From/To dialog, if more than one task meets the criteria you have specified.

The dialog displays the following information about each task that meets the linking criteria:
Field | Description |
---|---|
Create link | Select this check box to create a link to or from a task. If you are moving a link from one task to another, you can only select a single task. |
Name | The name of the task. |
Type | The type of task, for example Task or Milestone. |
Parent | The |
WBS code | The WBS code of the task. |
Task ID (WBN) | The task ID (WBN) of the task. |
UTID | The unique task ID of the task. |
Path | The path to the task through the project hierarchy. |
Start date | The start date and time of the task. |
Finish date | The finish date and time of the task. |
How do I...

Select the check box to the left of the tasks to or from which you want to create links, then click OK. If you are moving a link from one task to another, you can only select a single task.
Asta Powerproject creates links between the task(s) you have selected in the bar chart and the task(s) you have selected in this dialog.
If