Reschedule Progress Period Warning dialog
You use the Reschedule Progress Period Warning dialog to check that you are straightening the progress line to the report date of the correct progress period when you carry out a reschedule.

The Reschedule Progress Period Warning dialog appears when you reschedule a project, having specified to straighten the progress line to the report date of a specific progress period.
Normally when you carry out a reschedule, you will want to straighten the progress line to the report date of the progress period that you have most recently used to mark progress - the progress entry period.
The dialog shows you which progress period you are straightening the progress line to, and which is the current progress entry period. This ensures that you do not straighten the progress line to the report date of the wrong progress period accidentally.

Field | Description |
---|---|
Straighten progress period | The progress period whose report date you have chosen to straighten the progress line to during the reschedule. Select a different progress period if required, to straighten the progress line to that progress period's report date. |
Progress entry period | The current progress entry period - the one that has most recently been used to mark progress. Select a different progress period if required, to change the current progress entry period. |
Do not warn again | Select this check box if you do not want to see this dialog each time you reschedule. |
How do I...

Change either of the progress periods if required, then click OK to continue with the reschedule, or Cancel to close the dialog without rescheduling.
If you do not want to see this dialog each time you reschedule, select the Do not warn again check box.