Date Zone Properties dialog - Shading tab

You use the Shading tab of the Date Zone Properties dialog to specify one or more ranges of dates between which you want to shade the bar chart. You may want to shade the bar chart between a range of dates for a variety of reasons - for example, to highlight crucial periods in a project. This date range shading is completely separate to the non-working time shading that may appear on the bar chart.

You can shade the bar chart between more than one range of dates and apply a different style of shading to each date range shading selection. If one range of dates overlaps with another, the shading is drawn on the bar chart in the order in which the date range shading selections appear in the dialog, so the shading of the first date range will be overlaid by the shading of any date range below that overlaps.

You can copy date range shading selections from one view to another - in the same project, or in a different project if required. Copying shading selections between views enables you to set up shading selections in one view and apply them to other views easily.

How do I...

Related Topics:

Working with dialogs

Using the date zone

Shading the bar chart between two dates

Using variable dates such as 'Today' or 'Tomorrow'