Calendar Settings dialog

You use the Calendar Settings dialog to specify whether you want to use the calendar that you have just chosen to be the default for new tasks for folding away non-working time in the date zone and for displaying non-working time on subheading bars. You may wish to use the same calendar for all three purposes in order to synchronise the way in which you view your project information.

If you have removed the default setting from a calendar without having selected a different default calendar, you use this dialog to specify whether you want the change to apply to the date zone folding calendar and the subheading calendar too.

Related Topics:

Working with dialogs

Specifying which calendar to use by default