Block Link Method dialog
You use the Block Link Method dialog to specify the way in which you want to link the currently-selected tasks or bars, in cases where there is more than one task selected on each bar. You can either link the last task on the preceding bar to the first task on the succeeding bar, or link the first task on the preceding bar to the first task on the succeeding bar, the second to the second, and so on. Finish-to-start links are drawn between the tasks using the specified method.

The Block Link Method dialog appears when you link tasks when there is more than one task selected on a bar.

Field | Description |
---|---|
Last to first links | Click this radio button to link the last task on the preceding bar to the first task on the succeeding bar. |
Corresponding task links | Click this radio button to link the first task on the preceding bar to the first task on the succeeding bar, the second task on the preceding bar to the second task on the succeeding bar, and so on. |