Linking tasks on the same bar
You can draw links between consecutive tasks on the same bar, for example to ensure that there is a particular delay between the end of one task and the start of the next:
When you draw a link between tasks on the same bar, the link is represented as a horizontal line between the tasks.
You can only draw FS links from the first task to the second task, or SF links from the second task to the first task; you cannot draw links from the middle of one task to the middle of another task on the same bar.
If you draw a link between tasks whose owning tasks are
Reflected links show the existence of a link between two
If both owning tasks are expanded in situ, then the link is drawn as a normal link between the two tasks.