Asta Powerproject 2026.1 (18.0.04.001) release notes

This topic lists the new features that have been introduced, and the issues that have been addressed, in the Asta Powerproject 2026.1 (18.0.04.001) release.

DevOps Work Item 13022
Category Import and export
Summary Milestone types change when exporting a project into XER format.
Description A customer reported that when they exported a project into XER format, start milestones were incorrectly converted into finish milestones during the export, and appeared as finish milestones in the resulting file.
Resolution

Start milestones are no longer incorrectly converted into finish milestones in projects when they are exported into XER format.

 