Asta Powerproject version 15.0.02.405 release notes
This topic lists the issues that have been addressed in the Asta Powerproject version 15.0.02.405 fast track release.
| Issue | 32617 | ||||
| Category | Progress | ||||
| Summary | Incorrect overall percent complete values displayed against parent tasks. | ||||
| Description |
When you use the Baseline/What If Manager to create a baseline in Asta Powerproject, overall percent weightings are calculated for all tasks in the project before the baseline is created. This ensures that correct overall percent complete values are displayed against parent tasks in both the project and in the baseline as you move forwards with your planning.
Before this release, the calculation of task weightings was not carried out at any other point in the project lifestyle. For example, weightings were not calculated if you created a baseline by taking a copy of a project and importing it as a baseline, which resulted in incorrect overall percent complete values being displayed against parent tasks. |
||||
| Resolution |
Asta Powerproject now uses the duration of a task as its weighting, unless you have specifically edited a task's weighting, in which case the weighting you have specified is used. This ensures that accurate overall percent complete values are always displayed against parent tasks.
You may notice when you upgrade to this release that the overall percent complete values that are displayed against parent tasks have changed. The values are now more accurate, as task duration or weighting is now always taken into consideration when rolling up values to summary and expanded tasks. |
||||