Resource usage view pane
The resource usage view pane is displayed when you display a resource usage view in order to display the planned or actual assignments for one or more resources or cost centres on a daily, weekly, monthly or quarterly basis. The resource usage view pane appears below the spreadsheet and bar chart, attached to the bottom of them.
You can scroll around the resource usage view pane independently to the bar chart and spreadsheet. You can pan around the right-hand section of the resource usage view pane by holding down ALT on the keyboard then clicking and dragging in the pane, holding down the left mouse button as you do so. As you click and drag, the mouse pointer changes to .
You can also resize the resource usage view pane.