Move finish date right

Click Move finish date right to move the finish dates of the selected tasks or links to the right within the bar chart, ie to a later date. The finish dates of the selected tasks or links move right by one of the current snapping time units each time you click the control. For example, if the current snapping time unit is weeks, the finish dates of the selected tasks or links move a week later.

The start dates of the selected tasks are not changed, so the tasks increase in duration by one of the snapping time units each time you click the control.

Related Topics:

Changing the duration of tasks