Resource Report dialog - Report Details tab
You use the Report Details tab of the Resource Report dialog to specify the type of resource report you want to produce and the time unit over which you want report values to be averaged.

To access the Resource Report dialog, right-click a report in Library Explorer and select Properties.

Field/Button | Description |
---|---|
Report name | Enter a description of the report. |
Resources to report on | Select the items on which you want to report. |
Report type | Specify the type of report you want to produce, for example Permanent resource, Consumable resource or Cost centre. |
Time slicing unit | Select the time unit over which you want report values to be averaged. The larger the time unit you select, the less detailed the report will be. For example, averaging values over a month will give less precise details than averaging over a day. |
Calendar for working time slice units | The length of an working time unit can differ between calendars: for example, a working day could be 6.5 hours long in one calendar and 8 hours long in another. If you select a working time unit in the Time slicing unit field, select the calendar that defines the length of the working time unit in this field. |
Execute | Click this button to produce the resource report. |
How do I...

- Enter a description of the report in the Report name field.
- Specify the type of report you want to produce, for example Permanent resource, Consumable resource or Cost centre, in the Report type field. The items on which you can report appear in the Resources to report on field. For example, if you are producing a permanent resource report, the permanent resources in the project appear.
- Select the items on which you want to report in the Resources to report on field.
- Select the time unit over which you want report values to be averaged in the Time slicing unit field.
- If you select a working time unit in the Time slicing unit field, select the calendar that defines the length of the working time unit in the Calendar for working time slice units field.
- Use the other tabs of the Resource Report dialog to further specify information you want to include in the report, then click Execute to produce the report.
Specifying the type of resource report to produce
Specifying the time unit over which to average resource report values