Change Task Calendar dialog

You use the Change Task Calendar dialog to specify what you want to happen when you assign a different calendar to a task. Assigning a different calendar to a task may alter its duration or start and finish dates for the following reasons:

  • The time units in the calendars may differ in absolute terms. For example, a working week may be 5d in one calendar and 6 in another, or a working day may be 7h in one calendar and 8 in another.
  • The calendars may have different holidays, overtime and other exceptions. For example, if a task that starts on 1st June will not be able to start on that date if you assign a calendar to it in which 1st June is a holiday.

Related Topics:

Working with dialogs

Assigning a calendar to a task or resource