Questions you can answer by modelling resources

Modelling resources enables you to make trade-off decisions, such as weighing up the pros and cons of assigning more resources to a task and the impact this could have on costs and project finish dates. Modelling resources can help you answer questions like the following.

How long will it take to complete a task?

I have four painters available to work on a task that would take one painter fifty hours to complete. How long will the task take to be completed?

How much longer will it take to complete a task if I have fewer resources available?

I currently have eight electricians assigned to a task, but I have since found out that only five will be available. How much longer will the task take to be completed?

How many resources do I have to assign to a task for it to be completed on time?

Example 1: with a single resource assigned

A task has the following attributes:

  • Task: Formwork; duration: 37.5 hours.
  • Formwork: 300 square metres; output per carpenter: 2.5 square metres per hour.

How do I find out how many resources I need to complete the task?

Example 2: with two resources assigned

A task has the following attributes:

  • Task: Formwork & Reinforcement; duration: 37.5 hours.
  • Formwork: 300 square metres; output per carpenter: 2.5 square metres per hour.
  • Reinforcement: 0.4 tonnes; output per steel fixer: 0.045 tonnes per hour.

How do I find out how many resources I need to complete the task?

How can I calculate the rate at which a resource will have to work?

I know how many carpenters I have available to work on a 37.5 hour long task and I know the amount of work that needs to be done. At what rate will the carpenters have to work in order to complete the task?

How can I calculate the amount of work that is required to complete a task?

I know how the number of resources I have available, their work rate, and the duration of a task. How much work will the resources be able to carry out in the time available?

How many lorries do I need to deliver the materials required for a task?

I know that a task requires 103m3 of concrete and that each concrete mixer lorry has a capacity of 8m3. How many lorries do I need to deliver the concrete?